Appendix A - Sample Con gurations
Lead/Lag Controller Technical Guide
44
Lead/Lag Example - Controlling 3 Sets of Pumps
Binary Input Con guration
Binary Enable Input #1 is a switch that can start and stop the boiler
pumps.
Binary Enable Input #2 is a switch that can start and stop the chiller
pumps.
Binary Enable Input #3 is a switch that can start and stop the do-
mestic pumps.
Figure 82: Binary Enable Input 1 Con guration
Figure 83: Binary Proof Input 1 Con guration
Binary Proof Input #1 is a water ow switch for the boiler pumps.
Binary Proof Input #2 is a water ow switch for the chiller pumps.
Binary Proof Input #3 is a water ow switch for the domestic water
pumps.
See Figure 82 for the con guration for Binary Enable Input #1 and
Figure 83 for the con guration for Binary Input Proof #1.